NEWS

Updates on Downtown Improvement Plans

8/7/24 Update

GNO, Inc. Launches Website to Inform Residents of Road Closures

Greater New Orleans, Inc. is excited to announce the launch of nolastreets.info, a new website to keep residents informed about major road closures and infrastructure updates within the New Orleans “Entertainment District” as part of preparations for Super Bowl LIX in February 2025. The goal is to provide a quick and easy way for residents to see which roads are currently closed or partially closed at any given time.

8/5/24 Update

Poydras (Claiborne to Convention Center Blvd)

The City of New Orleans announced that starting Monday, Aug. 5 at 7PM, the Department of Public Works (DPW) contractor Hard Rock Construction, LLC will begin nighttime construction on Poydras Street, stretching from Convention Center Boulevard to S. Claiborne Avenue. The work will occur between 7PM and 5AM each night to minimize daytime traffic disruptions and expedite project completion, continuing through October 2024. This nighttime work is being completed in conjunction with the ongoing daytime work on Poydras Street.

During night closures, crews will facilitate roadway patching work, with two lanes of traffic remaining open at all times. Signage and traffic control measures, such as barrels and fencing, will be onsite to direct drivers and pedestrians.

What to Expect During Construction:

  • Noise Levels: The work involves milling and overlaying the road surface, producing noise levels similar to heavy trucks passing by. While there will be some noise from machinery and trucks, it will be minimal and not sustained in one area for long.
  • Visual Impact: Construction lights, essential for safety, will be directed downward to minimize light pollution and disturbance to nearby residents.
  • Duration and Timing: The work will progress quickly, limiting disturbances in any specific area.
  • Daytime Activities: More intensive tasks, like jackhammering, will be scheduled during the day to minimize nighttime disruptions. All work cannot be performed at night without causing major disturbances to residents and visitors; therefore, performing work at night where possible will minimize impacts and expedite the project timeline.

Daytime work on Poydras between Convention Center Boulevard to S. Claiborne Avenue will continue as scheduled, including roadway removal and replacement, re-striping, sidewalk repairs, installation of American with Disabilities Act-compliant ramps, and driveway apron repairs.

7/31/24 Update

Poydras (Claiborne to S. Liberty)

Scope:  Roadway removal and replacement, re-striping, sidewalk repairs, installation of Americans with Disabilities Act (ADA)-compliant ramps, and driveway apron repairs.

Lakebound: All street work and sidewalk repairs are substantially complete. Remaining work includes removing and replacing the turning lanes in both directions at Clara St. and removing and replacing a small section of the parking lane at 1515 Poydras St.

Riverbound: DPW crews are currently working in the left travel and turning lanes between Claiborne and Lasalle. Traffic has reopened to two lanes where possible. This week, DPW resumed work in the intersection of Poydras and Lasalle, where the Sewerage and Water Board (SWB) recently repaired a 36-inch waterline. The remaining work in this intersection includes a drainage point repair and roadway removal and replacement. All work in the riverbound lanes along this stretch of Poydras between Claiborne and S. Liberty is scheduled for completion by late August 2024.

Additionally, the traffic signal at Poydras and S. Robertson is being repaired. A power source upgrade from Entergy is required to complete the repair, which is expected to be finished by the end of this week.

Poydras (S. Liberty to Convention Center Blvd)

Scope: Patching, milling, and resurfacing the street, re-striping, sidewalk repairs, installation of Americans with Disabilities Act (ADA)-compliant ramps where needed, and driveway apron repairs

Roadway patching repairs began on Monday, July 22, 2024, and continue to progress. Milling and overlay work will follow. All work along this stretch of Poydras Street (S. Liberty – Convention Center Blvd.) is scheduled for completion by October 2024.

To minimize traffic impacts, crews will work in the lakebound lanes during morning rush hour and the riverbound lanes during evening rush hour, when possible. DPW is coordinating with the contractor to ensure that at the end of each day, all barricades and cones are removed, fully reopening the street to vehicular traffic. Additionally, they are exploring options for night work to further reduce daytime traffic disruptions.

Julia (Convention Center Blvd to Loyola)

Scope: Roadway removal and replacement, re-striping, sidewalk repairs, installation of Americans with Disabilities Act (ADA)-compliant ramps, and driveway apron repairs

Crews have completed repairs in the right travel lane and are removing the barricades from Camp St. to Loyola Ave. today. They have also finished work in the left travel lane and left parking lane between Convention Center Blvd. and Camp St. Beginning tomorrow, August 1, DPW’s construction contractor will temporarily demobilize, removing any cones or barricades from the 300-600 blocks of Julia Street. The remaining work will resume on Monday, August 5, and will include sidewalk repairs and work on the left side of the road from Camp to Loyola. All work on Julia Street is expected to be completed by early September.

Additionally, partners at SWBNO have repaired water leaks at all three locations on Julia Street (Julia and S. Peters, 450 Julia, and Baronne and Julia), and the city has completed permanent restoration at these sites.

Julia and Howard Extensions

Scope: Patching, milling, and resurfacing the street, and various sidewalk repairs

Asphalt and brickwork are substantially complete. Crews are currently addressing final punch list items.

Girod (Loyola to S. Liberty)

Scope: Patching, milling, and resurfacing the street, re-striping, and various sidewalk repairs

Street repairs are scheduled to begin this week, followed by sidewalk repairs. Access to the parking garage will be maintained throughout construction. All work is expected to last approximately six weeks, weather dependent.

 

7/23/24 Update

Poydras (Claiborne to S. Liberty)

Scope: Roadway resurfacing, re-striping, sidewalk repairs, installation of Americans with Disabilities Act (ADA)-compliant ramps, and driveway apron repairs

Lakebound: All street work and sidewalk repairs are substantially complete. Remaining work includes resurfacing the turning lanes in both directions at Clara St. and resurfacing a small section of the parking lane at 1515 Poydras St.

Riverbound: DPW crews are currently working in the middle travel lanes between Claiborne and S. Liberty. Once this is completed, work will shift to the left travel lane and turning lane. Traffic is currently restricted to one lane but will reopen to two lanes next week where possible. This week, DPW resumed work in the intersection of Poydras and Lasalle, where the Sewerage and Water Board (SWB) recently repaired a 36-inch waterline. Remaining work in this intersection includes a drainage point repair and roadway resurfacing.

All work in the riverbound lanes along this stretch of Poydras between Claiborne and S. Liberty is scheduled for completion by August 2024. Additionally, the traffic signal at Poydras and S. Robertson is scheduled for repair.

Poydras (S. Liberty to Convention Center Blvd)

Scope: Patching, milling, and overlaying the street, re-striping, sidewalk repairs, installation of Americans with Disabilities Act (ADA)-compliant ramps, and driveway apron repairs

Work is ongoing, with roadway patching repairs beginning on Monday, July 22, 2024. Milling and overlay work will follow. All work along this stretch of Poydras Street (S. Liberty – Convention Center Blvd.) is scheduled for completion by October 2024.

To minimize traffic impacts, crews will work in the lakebound lanes during morning rush hour and the riverbound lanes during evening rush hour. Crews will be working in three blocks at a time. At the end of each day, all barricades and cones will be removed, fully reopening the street to vehicular traffic. DPW is exploring options for night work to reduce daytime traffic disruptions.

Julia (Convention Center Blvd to Loyola)

Scope: Roadway resurfacing, re-striping, sidewalk repairs, installation of Americans with Disabilities Act (ADA)-compliant ramps, and driveway apron repairs

Crews have finished repairs in the right travel lane. Simultaneous crews are working in the left travel lane and left parking lane between S. Peters and Magazine St., as well as performing sidewalk repairs along Julia St.

Due to weather delays and unforeseen underground water leaks, street work will extend beyond the originally scheduled completion date of July 31. Additionally, the Sewerage and Water Board (SWB) is addressing water leaks at various locations on Julia Street. On August 1, the DPW’s construction contractor will temporarily demobilize, removing any cones or barricades from the 300-600 blocks of Julia Street. The remaining work will resume on Monday, August 5.

Julia and Howard Extensions

Scope: Patching, milling, and overlaying the street, and various sidewalk repairs

Asphalt work is substantially complete. Brickwork in front of the garage began this week and is expected to last approximately two weeks. Access to the garage will be maintained at all times.

Girod (Loyola to S. Liberty)

Scope: Patching, milling, and overlaying the street, re-striping, and various sidewalk repairs

Street repairs are scheduled to begin the first week of August, followed by sidewalk repairs starting the next week. Access to the parking garage will be maintained throughout construction. All work is expected to last approximately six weeks, weather dependent.

 

7/19/24 Update

Poydras (Claiborne to S. Liberty)

Scope: Roadway resurfacing including re-striping, sidewalk repairs, Americans with Disabilities Act (ADA)-compliant ramps, and driveway apron repairs.

Lakebound: All street work and sidewalk repairs are substantially complete.

Riverbound: DPW crews will continue working in the two left travel lanes between Claiborne and S. Liberty for the next couple of weeks. Traffic is currently restricted to one travel lane but will reopen to two travel lanes next week, except where the Sewerage and Water Board (SWB) is repairing a 36-inch waterline. DPW street repairs will resume at the Poydras and S. Liberty intersection once SWB completes the waterline repair.

All work in the riverbound lanes along this stretch of Poydras between Claiborne and S. Liberty is scheduled to be completed sometime in August 2024.

Poydras (Convention Center Blvd to Loyola)

Scope: Patching, milling, and overlaying the street, sidewalk repairs, Americans with Disabilities Act (ADA)-compliant ramps, and driveway apron repairs.

Work is ongoing, with roadway patching repairs now set to begin on Monday, July 22, 2024. Originally scheduled to start on July 15, the patching work was delayed a week. Milling and overlay work will follow. All roadwork along this stretch of Poydras Street between Convention Center Blvd and Loyola is scheduled for completion by October 2024.

To minimize traffic impacts, crews will work in the lakebound lanes during morning rush hour and the riverbound lanes during evening rush hour. Crews will be working in three blocks at a time. At the end of each day, all barricades and cones will be removed, fully reopening the street to vehicular traffic. DPW is exploring options for night work to reduce daytime traffic disruptions.

Julia (Convention Center Blvd to Loyola)

Scope: Roadway resurfacing, including re-striping, sidewalk repairs, Americans with Disabilities Act (ADA)-compliant ramps, and driveway apron repairs.

Crews have finished repairs in the right travel lane and parking lane from Convention Center Blvd to Church and are currently progressing from Church to Loyola. Simultaneous crews are working on the left travel lane and left parking lane between S. Peters and Magazine St, as well as performing sidewalk repairs on Julia.

By July 31, 2024, DPW’s contractor is scheduled to complete all roadway repairs. This leaves only incidental work on Julia to be wrapped up in August. In the unlikely event that the street work extends beyond this timeframe, the contractor will temporarily demobilize, removing any cones or barricades in the 300-600 blocks of Julia St., and resume the remaining work on Monday, August 5.

Julia and Howard Extensions

Scope: Patching, milling, and overlaying the street, and various sidewalk repairs.

Work is substantially complete.

Never Miss a Thing

SUBSCRIBE TO OUR NEWSLETTER

This field is for validation purposes and should be left unchanged.

More News from Downtown